Completion of the first water electrolysis system project

페이지 정보

작성일 22-02-10 16:35

본문

9a1897ccdfbc9cc65e0208ebd9a41451_1644478473_3555.JPG
 

On July 28, 2021, the water electrolysis system, which was ordered from Elchemtech and manufactured for about five months (August to December), was delivered on January 9 of this year and completed the site installation on the 12th. The product is the first water electrolysis project conducted as a business partner with Elchemtech, and it was carried out as an EPC product from basic design to trial operation.
 
The water electrolysis system ordered by Korea Hydro & Nuclear Power was overall produced by Sunbo, including the water electrolysis stack supplied by Elchemtech and the power conversion device supplied by Zipilos. In particular, this water electrolysis system applies plant specifications for the commercialization of water electrolysis in the future, implementing a design differentiated from the existing water electrolysis system.
 
Starting with the Korea Hydro & Nuclear Power Project, Doosan Heavy Industries & Construction has completed orders for 300KW (Jeju Island), and it is expected that customers' water supply needs will increase significantly in 2022. It is expected that the successful delivery of the KHNP's water electrolysis project will accelerate the growth of the "SUNBO Eco System" that will create new value for our company.